| Inbound Pena Boulevard Reconstruction Station 2243 to 2327+20
|
- Awarded To: Castle Rock Construction
- Contract Date: 07/19/2011
- Contract Amount: $3,196,023
- Bids Received
|
| HVAC Control Upgrades - Phase 3
|
- Awarded To: Intermountain Electric, Inc.
- Contract Date: 05/25/2011
- Contract Amount: $735,455
- Bids Received
|
| Pikes Peak Parking Lot Rehabilitation 2011
|
- Awarded To: Bangert Contracting Services, Inc.
- Contract Date: 06/30/2011
- Contract Amount: $1,500,000
- Bids Received
|
| Terminal Water Quality Pond
|
- Awarded To: American West Construction
- Contract Date: 08/16/2011
- Contract Amount: $1,307,082
- Bids Received
|
| Miscellaneous Roadway & Parking Lot Improvements 2011
|
- Awarded To: Interstate Highway Construction, Inc.
- Contract Date: 06/01/2011
- Contract Amount: $2,249,756
- Bids Received
|
| 2011 Annual Airfield Joint Rehabilitation
|
- Awarded To: Penhall Company
- Contract Date: 06/02/2011
- Contract Amount: $2,131,625
- Bids Received
|
| 2011 Annual Airfield Pavement Rehabilitation
|
- Awarded To: Interstate Highway Construction, Inc.
- Contract Date: 07/15/2011
- Contract Amount: $4,356,738
- Bids Received
|
| Runway 8-26 Complex Pavement Rehabilitation and ADG V Improvements
|
- Awarded To: Interstate Highway Construction, Inc.
- Contract Date: 08/12/2011
- Contract Amount: $19,152,540
- Bids Received
|
| Central Plant Cooling Tower Sump Separation
|
- Awarded To: Trautman & Shreve, Inc.
- Contract Date: 10/21/2011
- Contract Amount: $4,211,354
- Bids Received
|
| Hydronic System Optimization
|
- Awarded To: Trautman & Shreve, Inc.
- Contract Date:
- Contract Amount: $7,382,465
- Bids Received
|
| Filing 18 Phase 4 Asbestos Remediation Project
|
- Awarded To: Belfor Environmental Inc.
- Contract Date: 04/27/2011
- Contract Amount: $1,620,774
- Bids Received
|
| 2011 Parking Structure Repairs and Moisture Protection - Level 5
|
- Awarded To: John Rohrer Contracting Co. Inc.
- Contract Date: 02/25/2011
- Contract Amount: $3,474,679
- Bids Received
|